Page ContentThis case awarded liquidated damages against a surety under a performance bond. The case is notable because the prevailing view in Canada, at least until now, has been that a surety is only liable for the direct damages incurred by the owner in the completion of the project, and the surety is not liable for damages for delay, either general or liquidated. Case Comment - Lac La Ronge Indian Band v. Dallas Contracting Ltd. and Western Surety Company, 2001 SKQB 135